FAST – preserving the future

Although Fawley’s FAST project has been temporarily postponed, work continues at pace to ensure the project is well placed upon restart. Newsline has spoken to Yuri Cordy, project manager to discover what’s been happening to store and preserve the equipment already procured.
Image

Yuri has been working on the FAST project since May 2018, and now oversees the team managing equipment preservation and restart planning. To ensure its restart is a success, Yuri and his team have been working hard to ensure that the equipment is preserved in the same state as when first manufactured.

“Fairly soon after halting work on the construction site, we quickly moved onto finding ways to store and preserve all of our equipment,” he says. “This included small components such as pumps and valves to very large items such as reactors, towers and compressors plus everything in between.

Equipment that has already been delivered has been accommodated at an adjacent site in Fawley, or on the refinery itself including a new reactor and some very large columns. “Whilst the initial plan was to leave the columns at the supplier in the North of England, we have now managed to store these at Fawley in order to save costs,” says Yuri.

But with logistics constraints and the decision to defer certain activities such as refractory installation, Yuri and his team spent the second half of 2020 sourcing new storage facilities, negotiating storage with suppliers and devising preservation and inspection processes. “With items being procured from all over the world, we’ve even created a global map to show where all the equipment is located,” he adds.

Yuri explains that some equipment yet to be delivered is being stored with vendors at their manufacturing plants. “The modular part of the project is constructed in China, so we’ve had to arrange for the module equipment to remain in storage there. The same has applied to equipment procured from vendors in other locations such as Spain, Germany, Greece and Italy, where for example, large reciprocating compressors featuring very sensitive components, measuring 15 metres x 6 metres and weighing 165 tons each, have been engineered and are now preserved and stored under the responsibility of the supplier.”

But the story doesn’t end there, as the project team needs to regularly assess the condition of the stored items to ensure they do not deteriorate. A team of four are staying on the project to oversee this, working to a tight programme of inspections, and regular liaison with suppliers. As COVID-19 has made international travel difficult, external intermediaries have also been appointed to undertake inspections overseas on ExxonMobil’s behalf.

When asked what the main challenge has been during this unprecedented time, Yuri says, “renegotiating with vendors to ensure value for money” and “gaining a clear understanding of how they might store equipment” has been difficult without face-to-face meetings. “We’ve had to start from the bottom up and look at every single piece of equipment, continuously taking risk-based decisions around preservation,” he replies.

The FAST team has reduced in size but the current team is now fully in project restart preparation mode. “We want to use the duration of the construction pause wisely and continue to pursue initiatives that will reduce the cost and increase the value for money the project brings to Fawley.” A re-evaluation of the project has allowed the team to remove some facilities such as a storage tank from the scope, while further integration of the project team with construction and refinery partners can deliver a lower cost but more efficient project. The FAST project was one of a number of projects to be postponed in 2020. “This is a situation where we just don't have a playbook,” reveals Yuri. “Many lessons are being learnt along the way and we are sharing our experiences with other project teams facing similar issues. But thanks to the hard work and commitment of my team, we are confident that when we restart the FAST project, the equipment we have purchased and stored will be ready to go.”

Image
Image

Also in this issue

Travis takes the helm as RRT Coordinator

Travis takes the helm as RRT Coordinator

Travis Hansen, regional EP&R adviser has been appointed to lead the Regional Response Team (RRT) following the retirement of Mark Wentworth (see Newsline April 2021). “I’ve been involved with the RRT since 2013 and when Mark retired, I felt I could do something to build on the amazing job he’s done and bring my own energies to the role,” he says.
Fawley helps in COVID-19 fight

Fawley helps in COVID-19 fight

As the battle against COVID-19 continues, ExxonMobil Fawley has become a key player in the global vaccine supply chain. The site’s Chemicals units are responsible for supplying a range of products including halobutyl rubber, a component of the vaccine vials.
PIGs in the pipeline at FEP

PIGs in the pipeline at FEP

This is not your usual PIG – this is a Pipeline Inspection Gauge, a specialist robot that checks and cleans oil and gas pipelines from the inside to keep them running safely, using a process known as ‘pigging’. As part of the £140m plant investment programme now underway at our Fife Ethylene Plant, we are pigging the 7km of pipes that link the plant to our Braefoot Bay Marine Terminal on the Forth.
Helping Hampshires Search  Rescue Heroes

Helping Hampshire’s Search & Rescue Heroes

Hampshire Search and Rescue is one of the latest voluntary organisations to receive a donation from the ExxonMobil VIP scheme. £500 was awarded to the charity, which works alongside Hampshire police in searching for vulnerable high risk missing persons in the county. The team has been called out 30 times so far this year and the donation will go towards new lifejackets for river bank searching.
Remediation works are set to begin at Bowling

Remediation works are set to begin at Bowling

Preparation and construction works are due to start this month (May) at a significant former industrial site in Bowling near Glasgow after a year-long delay due to COVID-19. As part of the land sale agreement, ExxonMobil will remediate the site, which was previously home to an Esso oil terminal. The land is now part of the Glasgow City Region Deal project and will be transformed by the buyer into a major industrial and commercial development and bypass.
Fawley prepares for 70th anniversary celebrations

Fawley prepares for 70th anniversary celebrations

Preparations are underway to mark the 70th anniversary of the ‘new’ refinery at Fawley in September. Newsline spoke to Alison Jones, Fawley community manager, who is helping to co-ordinate the celebrations with Fawley’s Behaviours and Culture team.

“Everything at Fawley has 70th anniversary branding this year,” says Alison. “The 10 large information boards displayed in Fawley’s conference centre are being upgraded to mark the anniversary and digital signage is being used across the site. New photographs have been commissioned to hang throughout the administration building too.