Remediation works are set to begin at Bowling

Preparation and construction works are due to start this month (May) at a significant former industrial site in Bowling near Glasgow after a year-long delay due to COVID-19. As part of the land sale agreement, ExxonMobil will remediate the site, which was previously home to an Esso oil terminal. The land is now part of the Glasgow City Region Deal project and will be transformed by the buyer into a major industrial and commercial development and bypass.
Image

James Hadwen is ExxonMobil’s Senior Project Manager for the remediation works. “Our work is relatively simple in many respects,” he says, speaking to Newsline. “It is essentially a large-scale civil earthworks programme to enable the redevelopment of the site. We're going to dig out some 200,000 cubic metres of soil, treat a portion of it to extract contamination using a novel soil washing approach, and then replace the clean material back into the ground.”

Delve a little deeper however, and the remediation work is not as simple as James describes! The site is mostly reclaimed land that borders the River Clyde and as the earthworks extend right to the edge of the site the project will have to deal with river and groundwater tidal fluctuations of up to 3m and the occasional storm that will make stability and water management a tricky business. A substantial section of the river edge will need to be physically removed and then replaced and finished with a new rock armour wall.

James explains that site access is challenging too. “There is only one vehicular access bridge to the site and to enable remediation works to take place, a temporary ‘Bailey bridge’ will need to be placed on top of the bridge which has a limiting weight restriction. This portable, prefabricated truss bridge - as used by the military in the Second World War to cross rivers – will unfurl to take the weight of all of the trucks and equipment entering and exiting the site, leaving the original bridge structure uncompromised,” he says.

Image

“This work has the potential to generate odour, dust and vibration which we will need to manage along the way too, in order to respect both the environmental regulations and the needs of the local residents bordering the site.”

A remediation contractor and an environmental consultant will support James on the project, which will see 15 to 35 people on site during the process. Measures will be put in place to mitigate odours and noise caused by treatment works and James stresses the importance of rolling out a pro-active communications plan to ensure nearby residents and stakeholders are kept informed.

Works were originally due to begin a year ago, but have been delayed due to COVID-19. However, James says that the delays have given him an opportunity to modify the project, having joined the team after the initial design work had been completed. “The groundbreaking work is now likely to start in July and will run for two and a half years, but there are many things that could affect that timeline, not least the potential for further travel restrictions or lockdowns in Belgium and France where the site contractor comes from.”

There are also the added complications of operating a COVID-safe environment. He adds: “We need to ensure support services, such as geotechnical and analytical laboratories are open, and we’ve adjusted our shift pattens to take account of travel restrictions, quarantines and Brexit licensing complexities too. We need to have COVID testing for the team and social distancing for the office areas on site. Important consideration and careful management of communal decontamination areas including showering, dressing and changing facilities will be needed too.”

James sums up the project nicely when he concludes: “All the devil is obviously in the detail.” Newsline will catch up with him again later this year to find out how things progress.

Also in this issue

FAST  preserving the future

FAST – preserving the future

Although Fawley’s FAST project has been temporarily postponed, work continues at pace to ensure the project is well placed upon restart. Newsline has spoken to Yuri Cordy, project manager to discover what’s been happening to store and preserve the equipment already procured.
EMBRACE  its time to talk

EMBRACE – it’s time to talk

Conversations about race can sometimes feel uncomfortable – but that’s no reason not to speak out. Newsline recently spoke with Bhonae Tayali, EMIT digital support advisor, of the EMBRACE Network about its latest activities, which seek to show why we must actively listen, learn and talk about the experiences of our colleagues from ethnic minority backgrounds, in order to live out the ExxonMobil value of being inclusive.
Fawley prepares for 70th anniversary celebrations

Fawley prepares for 70th anniversary celebrations

Preparations are underway to mark the 70th anniversary of the ‘new’ refinery at Fawley in September. Newsline spoke to Alison Jones, Fawley community manager, who is helping to co-ordinate the celebrations with Fawley’s Behaviours and Culture team.

“Everything at Fawley has 70th anniversary branding this year,” says Alison. “The 10 large information boards displayed in Fawley’s conference centre are being upgraded to mark the anniversary and digital signage is being used across the site. New photographs have been commissioned to hang throughout the administration building too.

Project protects nesting oyster catchers

Project protects nesting oyster catchers

Project planners at our Fife Ethylene Plant considered many different scenarios in the run up to the current £140m upgrade – but discovering a protected bird’s nest wasn’t one of them!